DIGITAL INFRASTRUCTURE / INVESTMENT INTELLIGENCERESEARCH PLATFORM · DATA CENTER FULL CYCLE INDEX · DATA AS OF 23 NOV 2026 · PUBLICATION LOG
DUK

Duke Energy

Layer 1 · PowerPower & grid· NYSE, United StatesData under review
KEY FACTS · MARKET DATA 23 Nov 2026 · FINANCIALS FOR 12 MONTHS TO 30 Jun 2026
Market capitalization$101bnUSD
Enterprise value$192bnvendor figure ≈ market cap + net debt
Revenue, last 12 months$32.8bngrowth n/d
EBITDA margin50.7%standardized TTM EBITDA
EV / EBITDA11.6xtrailing
Net debt / EBITDA5.51xnet debt $91.5bn
Dividend yield3.35%indicated annual
P/E, last 12 months19.4xtrailing earnings
Data center exposuren/dtier per catalog

Primary report: 10-Q for the period ended 30 Sep 2026, filed 5 Nov 2026 (SEC EDGAR): the latest regular periodic report of the issuer. Check the financial figures of this page against its statements.

Check against the issuer's own filing (XBRL data)
FigureVendorFilingResult
Revenue, last 12 months (filing to 31 Mar 2026)$32.8bn$32.5bnfiling covers a later period than the vendor figure; refresh pending
Shares outstanding (cover page of the latest report)780m780magrees

Filing values are read automatically from the issuer's XBRL data filed with the SEC; the comparison is indicative. A difference is a prompt to open the report linked above, not proof that either number is wrong.

Net debt from the issuer's balance sheet (31 Mar 2026, grade B)
ComponentUSD
Financial debt$90.2bn
less cash and cash equivalents$2.1bn
ND-A, financial net debt$88.1bn
ND-B, with leases$88.1bn
plus non-controlling interests and preferred$2.0bn
ND-C, enterprise-value bridge$90.1bn
memo: restricted cash (not deducted)$112m

Calculated by the Net Debt Standard from the 10-Q filing balance sheet of 31 Mar 2026; a negative figure is net cash. Caveat: lease liability tags absent: ND-B equals ND-A; balance sheet 235 days old; short-term investments: tag last reported 2014-03-31, not at 2026-03-31 - possible omission; lease liabilities: tag last reported 2025-12-31, not at 2026-03-31 - possible omission; no short-term investment value at the date.

Source of these figures: a public market-data vendor (quote of 23 Nov 2026; financials are trailing twelve months to 30 Jun 2026). They are recomputed and checked for internal consistency but individual figures are not traced to filing lines; the linked documents support the company's role in data centers, not these numbers. Where a mining or capacity block below shows a different market cap or EV, it uses a later balance-sheet date, pro forma share count or the Value-per-MW definition (debt at face value, restricted cash counted as cash); the two are not meant to match.

WHAT THE BUSINESS SELLS

Power & grid: Generates or delivers electricity to large data center loads; exposure runs through power purchase agreements, interconnection queues and rate-base growth.

Duke Energy is classified in segment S1 · Power of the company catalog (admitted in catalog version 1.0). The classification rests on a documented role in the data center value chain: Duke Energy: Data center growth will deliver billions of dollars in customer savings | Duke Energy | News Center.

THE INVESTMENT QUESTIONS

What to understand before assigning value.

  1. How much contracted data center load is signed versus queued, and at what tariff structure and term?
  2. Does the rate base or the merchant generation fleet capture the load growth, and who bears the cost of new capacity?
  3. What regulatory or ratepayer-protection commitments limit the margin on large-load contracts?
  4. How is the dividend funded while capital expenditure rises?
DATA QUALITY NOTES
  • Year-over-year revenue growth is not disclosed on a comparable basis.
  • Two public sources disagree on trailing revenue; the catalog records both and does not compute year-over-year growth.