Bitcoin mining, data center and GPU cloud investment calculators.
Three unlevered, after-tax scenario models with annual cash flows. Each reports NPV, IRR and two break-evens (a break-even is shown as "No solution in range" when no value inside the search range makes the project work): the operating break-even that covers cash costs, and the investment break-even — the hashprice, tariff, rent or utilization at which the project returns its capital at your required rate.
Scenario models. Default values are illustrative assumptions, not live prices or forecasts, and they are deliberately not tuned to look attractive: at the defaults the mining and GPU cases do not earn their cost of capital, and the break-even panel tells you what would have to change. All amounts are USD.
Investment break-even
Annual net cash flow
Blue bars: positive cash flows. Brown bars: negative cash flows, shown by magnitude. Final year includes residual or exit value. The initial investment appears in the table.
Assumptions & model boundaries
View the complete annual cash-flow schedule
| YEAR | REVENUE | OPERATING CASH PROFIT | TAX | MAINTENANCE | EXIT VALUE | NET CASH FLOW |
|---|
Formulas you can check by hand.
Hashprice to cash flow
Revenue = PH/s × hashprice × 365 × uptime × (1 − pool fee). Electricity = PH/s × J/TH × PUE × 24 × 365 × uptime × $/kWh. ASIC investment = PH/s × 1,000 × $/TH. Hashprice declines once a year by the entered rate. Depreciation straight-line over the holding period; tax on positive EBIT.
Read: the full cost of mining one bitcoin →Capacity to rent to exit
Base rent = IT MW × 1,000 × $/kW/month × 12 × occupancy; occupancy moves linearly to the stabilized level by year three. Opex and maintenance are percentages of build cost; power is passed through at cost. Exit value = final-year NOI ÷ exit cap rate, less 2% selling costs; depreciation over 30 years.
Read: what is a megawatt worth? →GPU-hours to hardware returns
Revenue = GPUs × 8,760 × utilization × realized $/GPU-hour, declining once a year by the entered rate. Power is charged for all 8,760 hours at system load × PUE × $/kWh regardless of utilization. No replacement purchase within the hardware life; residual value at exit.
Read: GPU cloud unit economics →Read the model before reading the return. NPV depends on the chosen discount rate; IRR may be unavailable for non-conventional cash flows; financing, construction delays, loss carry-forwards and terminal taxes are excluded. Formulas and limitations · Three worked cases.