Start with a project. Build an investment case.
Three worked starting points connect operating assumptions with cash flow, each opening directly in the calculator with the inputs pre-filled. They are illustrative cases, not investment offerings — and two of the three do not clear their hurdle rate at the default assumptions, which is the point of running them.
A 1 PH/s ASIC investment
Equipment acquisition against an explicit hashprice path, energy tariff and operating schedule.
- 19 J/TH fleet efficiency, PUE 1.10
- 80% uptime and $0.06/kWh power
- Hashprice $50/PH/day, −12% a year
- Four-year holding period, 15% discount rate
Result: NPV −$7,571, IRR −22.4%. Operating break-even $34.90; investment break-even $62.70 hashprice or $0.039/kWh.
Open the complete scenario →A 10 MW data center
A lease-up schedule from first operations to stabilized occupancy and a year-ten sale.
- 10 MW of IT capacity at $10m per MW
- 50% initial, 85% stabilized occupancy by year 3
- $150/kW/month starting rent, +2% a year
- 8% exit capitalization rate, 12% discount rate
Result: NPV +$18.4m, IRR 14.5%. Rent of $130/kW/month or a build cost of $11.6m/MW would bring NPV to zero.
Open the complete scenario →A 128-GPU deployment
Whether realized pricing and billable utilization justify the installed hardware cost.
- $35,000 installed cost per GPU
- 65% billable utilization at $2.50 per GPU-hour
- 1.2 kW per GPU, PUE 1.25, $0.07/kWh
- Four-year hardware life, 18% discount rate
Result: NPV −$822k, IRR 8.2%. The capital is recovered at 81% utilization, $3.13 per GPU-hour or $26,800 per GPU.
Open the complete scenario →Three steps the calculators cannot take for you.
Asset and rights
Document land, interconnection, permits, ownership, IT capacity and customer requirements. A megawatt in a queue is not a megawatt behind a meter.
Cash and obligations
Reconcile construction schedules, customer payments, maintenance, taxes and committed funding — monthly during construction, not annually.
Return and downside
Test delays, lower utilization, weaker prices, refinancing and the residual asset value. The better allocation is the one that survives the downside case.