Key takeaways
- "Megawatt" describes at least four different assets: a utility interconnection, a permitted site with power secured, an energized building, and occupied IT load under lease. Each has its own cost to complete, time to cash flow and risk, and each deserves a different multiple.
- At the HASHFLOPS.IO data center defaults — 10 IT MW, $150/kW/month, 85% stabilized occupancy — base rent is $15.3m a year on a $100m build, and the project earns 14.5% unlevered against a 12% hurdle. Rent of $130/kW/month or a build cost of $11.6m per MW takes the NPV to zero.
- Enterprise value per MW is only meaningful when numerator and denominator cover the same assets. An EV that includes a Bitcoin treasury, a GPU fleet or a development pipeline cannot be divided by operating colocation capacity.
Start with the asset you actually own
The word "megawatt" is doing too much work in most data center pitches. A utility can grant a queue position for 300 MW that will not be energized for four years. A developer can own land with a signed interconnection agreement, a substation design and no building. An operator can own an energized shell with chillers, generators and raised floor but no tenant. And a landlord can collect rent on 50 MW of IT load under a fifteen-year lease. All four describe "a megawatt". Only the last one is a cash-flowing asset today.
Before comparing any transaction, pin down four things: the capacity definition (utility MW versus critical IT MW, which differ by the PUE and redundancy design), the ownership interest (fee simple, ground lease, joint venture share), the commissioning date, and the expenditure still required to reach occupied, billing load. A site with power secured but no building should carry a development-rights framework, not a stabilized-asset multiple.
Connect capacity to rent and cash flow
For a colocation asset the bridge from capacity to cash is short, but every step has a unit. Begin with IT capacity in kW, apply occupancy, and multiply by the rent per kW per month attributable to space and infrastructure. Keep electricity recoveries out of base rent: in most wholesale leases power is passed through at cost, so it inflates revenue without adding margin. Deduct facility operating costs, maintenance capital, property taxes and the capital still to be spent. What is left belongs to the owner — and only after debt service if the asset is levered.
The HASHFLOPS.IO data center model keeps these steps explicit. Ten IT megawatts are 10,000 kW; at $150 per kW per month and 85% occupancy, annual base rent is 10,000 × 150 × 12 × 0.85 = $15.3m. Operating costs of 2% of build cost ($2.0m) and maintenance of 1% ($1.0m) leave a stabilized net operating income before tax that the exit cap rate turns into a sale price in year ten. In the model the exit value capitalizes net operating income after operating costs (2% of build cost) but before the 1% maintenance reserve; maintenance is deducted from annual cash flow, not from the capitalized income, so a convention that deducts it before capitalization would lower the exit value. The point is not the specific numbers but the chain: kW → occupancy → rent → NOI → value, with power recoveries and construction spending kept in their own lines.
Worked example
| Input | Default | Output | Value |
|---|---|---|---|
| IT capacity | 10 MW | Investment at $10m per IT MW | $100m |
| Rent | $150/kW/month, +2% a year | Base rent at 85% occupancy | $15.3m a year |
| Occupancy path | 50% in year 1, 85% by year 3 | Operating break-even occupancy (opex only) | 11.1% |
| Opex / maintenance | 2% / 1% of build cost | Unlevered IRR, 10-year hold | 14.5% |
| Exit | 8% cap rate on year-10 NOI, less 2% costs | NPV at 12% discount rate | +$18.4m |
| Tax | 25% on positive EBIT, 30-year depreciation | Rent for NPV = 0 | $130/kW/month |
| Build cost for NPV = 0 | $11.6m per IT MW | ||
| Exit cap rate for NPV = 0 | 11.2% |
The investment break-evens are the useful part. A $20 per kW drop in achievable rent, or a 16% construction overrun, removes the entire excess return. An exit cap rate that widens from 8% to 11% does the same, which is why the exit assumption deserves as much scrutiny as the rent roll. Open the scenario with the defaults and move one input at a time.
Use a matching numerator and denominator
Enterprise value per MW is the sector's favorite shorthand and its most abused one. It works when both sides of the ratio cover the same assets and the same ownership: an enterprise value built from a data center REIT's debt and equity, divided by the operating IT megawatts that REIT consolidates. It stops working the moment the numerator includes something the denominator does not. A miner-turned-landlord with a Bitcoin treasury, a GPU cloud fleet and 1 GW of "pipeline" cannot be valued by dividing its EV by the 100 MW of colocation it has actually leased; the result will look absurdly expensive per MW and tell you nothing.
Two corrections make the ratio usable. Either attribute value to the other assets first — treasury at market less tax, GPUs at a discounted replacement cost, pipeline at a development-rights value — and divide only the residual EV by operating MW. Or disclose the mismatch and treat the resulting number as a ceiling, not a comparable. The same discipline applies to per-MW transaction prices: a powered-shell sale at $8m per MW and a stabilized, leased campus at $14m per MW are not the same market.
What changes the investment case
The most useful sensitivities are not margins. They are time to energization, cost to complete, occupancy, rent, tenant credit and exit cap rate — the variables that move the timing and the certainty of the cash flows. A twelve-month construction delay matters more than a two-point improvement in operating margin, because it postpones every receipt while the capital stays committed, and because the tenant who signed for 2027 may not wait until 2028. Tenant credit decides what the lease is worth if the market turns: a fifteen-year lease to a hyperscaler and a fifteen-year lease to a venture-funded AI start-up should not carry the same cap rate even if the rent per kW is identical.
Publish an explicit base case and show the assumptions that would invalidate it. In the catalog behind this site, the operators with the most AI-related revenue today — Core Scientific at 83% of Q2 2026 revenue from colocation, TeraWulf at 71% from HPC leases, Applied Digital at 78% including a large one-off fit-out component — are also the ones whose valuations depend most on contracted-but-not-yet-built megawatts. Read their profiles with the stage of each megawatt in mind: CORZ, WULF, APLD.
Questions to ask before investing
- Is the capacity quoted in utility MW or critical IT MW, and at what PUE and redundancy level?
- For each megawatt, what stage is it at: queued, secured, energized, built, leased, billing?
- How much capital is still required to reach billing load, and who funds it?
- Does the rent per kW include power, and how are power price changes passed through?
- What is the tenant's credit, lease term, escalator and termination right?
- Does the EV used in any per-MW comparison include assets that are not in the MW count?
- At what rent, build cost and exit cap rate does the project stop earning its cost of capital?
Sources
- HASHFLOPS.IO data center model v1.1 — formulas and defaults on the methodology page.
- DC/AI company catalog 1.2, snapshot 10 Oct 2026 — issuer Q2 2026 releases for Core Scientific, TeraWulf and Applied Digital (linked on each profile).
- DC Byte, data center market coverage: https://www.dcbyte.com/
The analytical framework and worked examples are HASHFLOPS.IO editorial analysis. Numerical examples use stated assumptions and are not current market quotations. Nothing on this page is investment advice or an offer; see the disclaimer.