Key takeaways
- Between "announced capacity" and "cash flow" sit six milestones — power secured, permits, financing, construction, commissioning, billing commencement — and each one can slip, shrink or fail. A pipeline is a probability-weighted option, not a revenue line.
- In the HASHFLOPS.IO data center model, moving year-one occupancy from 50% to 85% changes the NPV, but a one-year delay in first revenue costs more than the ramp does, because the capital is committed from day zero.
- The catalog separates issuers whose AI revenue is operating (Core Scientific, TeraWulf, Applied Digital, IREN) from those admitted on signed contracts alone (Hut 8, Cipher). The distinction is the whole valuation question.
A gigawatt in a press release
Every month a listed company announces a new campus: 400 MW here, 1.2 GW there, "potential capacity" measured in the thousands of megawatts. The number is real in the sense that someone has filed a utility request or optioned land. It is not real in the sense that matters to an investor: nobody is paying for it yet, and the sum of money between the announcement and the first invoice is usually several times the company's current enterprise value. The task is to convert announced capacity into expected cash flow — with dates, costs and probabilities attached.
The conversion runs through milestones. The order varies, but the list rarely does.
The six milestones
1. Power secured. An interconnection agreement with a utility or an independent power producer, with a capacity in MW, an energization schedule and a tariff structure. A queue position is not power secured; a signed agreement with milestone payments is. Ask for the energization date and what happens if the utility misses it.
2. Site control and permits. Land owned or under long-term lease, zoning for data center use, water and environmental permits, and — increasingly — community agreements on noise and local power prices. A site can hold power and still lose a year to permitting.
3. Customer commitment. A letter of intent is marketing. A signed lease or hosting agreement with a commencement date, a rent per kW, an escalator, service-level credits and a termination schedule is a contract. Even a contract has conditions precedent: delivery dates, acceptance tests, and sometimes financing contingencies on the tenant's side.
4. Financing in place. Construction debt, equipment financing, prepayments from the tenant, or equity. The question is not whether the capital exists in the market but whether it is committed to this project under terms the project can afford. Many announced campuses are financed in tranches that depend on earlier tranches performing.
5. Construction and commissioning. Long-lead items — transformers, switchgear, generators, chillers — have had multi-year lead times in this cycle. Commissioning of a 100 MW hall is a months-long process of load banks, integrated systems tests and tenant acceptance. The press release says "delivered in Q3"; the lease says rent starts at "substantial completion as certified by the tenant's engineer".
6. Billing commencement and ramp. Rent typically starts in phases as halls are accepted, sometimes with free-rent periods or ramp schedules tied to the tenant's own equipment installation. Only here does capacity become cash flow — and only at the contracted rent, not at a market rent that may have moved since signing.
Haircut each milestone
Treat the pipeline as a decision tree. Assign each project a stage, a probability of reaching billing, an expected date and the remaining capital to complete. Multiply through. The result is usually a small fraction of the headline megawatts, with cash flows arriving later than the slide deck suggests. The haircuts are judgment, but they are better than the two alternatives most analysts actually use: counting the full pipeline as revenue, or ignoring it entirely.
Two signals deserve weight. Prepayments and tenant-funded fit-out shift risk from the landlord to the customer and are strong evidence of commitment — Applied Digital's $152.4m of tenant fit-out revenue in the quarter to 31 May 2026 is the clearest example in the catalog, though it is one-off revenue and must not be capitalized as rent. Conversely, a campus whose customer is itself pre-revenue, or whose financing depends on the customer's own fundraising, carries correlated risk: if the AI tenant stumbles, the landlord's contract and its credit go together.
Worked example
The HASHFLOPS.IO data center model does not model construction delay explicitly — operations start in year one by assumption — but the ramp inputs show how much timing matters relative to the headline capacity.
| Scenario (10 IT MW, $100m build, $150/kW/month, 12% discount rate) | Change | NPV | IRR |
|---|---|---|---|
| Base case | 50% occupancy in year 1, 85% by year 3 | +$18.4m | 14.5% |
| Faster lease-up | 85% from year 1 (pre-leased) | higher | higher |
| Slower lease-up | 30% in year 1, 85% by year 3 | lower | lower |
| Rent for NPV = 0 at base ramp | $130/kW/month | 0 | 12.0% |
| Build cost for NPV = 0 | $11.6m per IT MW | 0 | 12.0% |
Run the three ramps yourself using the presets on the calculator; the exact NPVs depend only on the inputs shown. What the model cannot show — and a real project model must — is a twelve-month delay before year one with the $100m already spent. Discounting every cash flow by one more year at 12% removes roughly 11% of the present value of the entire rent stream, more than the difference between the fast and slow lease-up cases. Delay is the expensive variable, and it is the one press releases never quantify.
What the catalog shows
The company catalog records, for each issuer, whether AI or HPC revenue is operating (reported in the income statement), contracted (signed leases, no separate revenue yet) or merely announced. As of the 10 Oct 2026 snapshot the picture among former and current Bitcoin miners is instructive:
- Operating, large share: Core Scientific (83% of Q2 2026 revenue from colocation), TeraWulf (71% from HPC leases), Applied Digital (78% of the May 2026 quarter, including the one-off fit-out).
- Operating, small share: IREN (18.2% AI cloud in FY2026), Bitdeer (6.1% in Q2 2026), HIVE (8.9% in the June 2026 quarter).
- Contracted, not yet reported: Hut 8 and Cipher, admitted on signed long-term AI leases.
- Delivered to a single tenant: Galaxy Digital, whose 133 MW Helios phase I produced $18.9m of leasing revenue in Q2 2026 against 526 MW contracted for fifteen years.
None of these facts says which equity is cheap. They say where each company sits on the six-milestone path, and therefore which questions its valuation must answer first.
Questions to ask before investing
- For every announced megawatt: which of the six milestones has been passed, with documents, and what is the dated schedule for the rest?
- How much capital remains to reach billing, and is it committed or assumed?
- Who is the tenant, what is its credit, and what conditions precedent sit between the signed lease and the first rent payment?
- Are prepayments or tenant fit-out contributions in place, and are they being reported as rent?
- What happens to the project economics if energization slips by twelve months?
- Is the operating revenue share quoted for a full year or a single quarter?
Sources
- HASHFLOPS.IO data center model v1.1 — methodology.
- DC/AI company catalog 1.2, snapshot 10 Oct 2026 — issuer releases for Core Scientific (28 Jul 2026), TeraWulf (5 Aug 2026), Applied Digital (27 Jul 2026), IREN (27 Aug 2026), Bitdeer (10 Aug 2026), HIVE (15 Aug 2026), Galaxy Digital (Q2 2026 release), Hut 8 and Cipher (Q2 2026 packages), as linked on the company profiles.
- DC Byte, data center market coverage: https://www.dcbyte.com/
The analytical framework and worked examples are HASHFLOPS.IO editorial analysis. Numerical examples use stated assumptions and are not current market quotations. Nothing on this page is investment advice or an offer; see the disclaimer.