STANDARD · MINING COST · 2026Q3

What it costs public miners to produce one bitcoin.

Production-weighted cash operating cost of $60,477 per BTC across four headline miners in Q3 2026, with energy, direct, cash-operating, business and full-cost layers from SEC filings; CLSK, CANG, FUFU pending at the data cut.

Version 1.0Published 17 Oct 2026Validation verdict: READY3101 words
$60,477cash operating cost per BTC (L1)
+16%cohort cash operating margin
4 of 15headline miners (3 pending)
1932engine values checked

Headline

  • Production-weighted cash operating cost (L1): $60,477 per BTC across 4 headline owner-operators (8,779 BTC mined in Q3 2026); median $56,739; range $49,604 – $83,763.
  • Production-weighted realized price $71,578 per BTC → cohort cash operating margin +15.5% of revenue, defined as (realized price − L1 cash operating cost) ÷ realized price = (71,578 − 60,477) ÷ 71,578. The same gap measured on cost (markup: price ÷ cost − 1) is 18.4%; this site uses the margin on revenue everywhere.
  • 3 of 4 headline miners covered cash operating cost from mining revenue in Q3 2026; MARA did not (L1 above realized price). On a full-accounting basis (L3, incl. attributable D&A) 8 of 8 Tier-1 miners with a computable stack had L3 above their realized price.
  • Energy (L0-E) is the most comparable layer: BTDR $36,083; HIVE $42,617; RIOT $45,723; MARA $39,674.
  • Like-for-like: the same 4 companies had a production-weighted L1 of $64,481 against a realized price of $71,621 in Q2 2026 (-6.2% cost, -0.1% price quarter on quarter). The previous release's six-company headline ($64,536 in Q2 2026) is not comparable: CleanSpark is pending and IREN fell below the 500 BTC threshold.
  • Not yet filed at the data cut: CleanSpark (CLSK). Carry-forward rule (owner decision 17 Nov 2026): until a company's new filing appears, its latest published quarter stays on the charts and tables, labelled with that quarter; CLSK is shown at Q2 2026 (previous release). Carried rows are outside the cohort statistics above and are replaced within one business day of the filing under the interim-update rule.

Headline table — Tier 1 owner-operators, ≥ 500 BTC mined in Q3 2026 (ranked by L1)

# Company Scope L0-E Energy/BTC L0 Direct NET/BTC L1 Cash operating/BTC L1 band 0%–100% L2 Cash business/BTC L3 Full/BTC Realized price Cash op. margin L1 TTM (4Q) BTC mined
1 Bitdeer (BTDR) E+S $36,083 $41,323 $49,604 $41,323 – $50,898 $57,292 $85,522 $71,958 +31% $57,042 3,855
2 HIVE Digital (HIVE) E+S $42,617 $47,060 $56,016 $47,060 – $57,058 $57,309 $103,240 $71,064 +21% $63,919 1,070
3 Riot Platforms (RIOT) E+S $45,723 $39,265 $57,461 $39,265 – $67,726 $58,534 $98,075 $70,855 +19% $69,109 1,637
4 MARA Holdings (MARA) E+S+H $39,674 $63,652 $83,763 $63,652 – $84,430 $89,644 $155,501 $71,699 -17% $88,514 2,217

Scope codes: E energy only · E+S energy + site opex · E+S* partial site scope (some site costs in SG&A) · E+S+H incl. third-party hosting · H hosted · H-RP related-party hosted.

Carried forward — latest published quarter of pending filers (not in the cohort statistics)

Company Scope Quarter carried L0-E Energy/BTC L0 Direct NET/BTC L1 Cash operating/BTC L1 band 0%–100% L2 Cash business/BTC L3 Full/BTC Realized price Cash op. margin L1 TTM (4Q) BTC mined
CleanSpark (CLSK) E Q2 2026 $44,432 $44,521 $61,570 $44,521 – $61,570 $62,633 $114,639 $71,878 +14% $64,832 1,920

Appendix — sub-threshold Tier 1, hosted / non-separable miners and pending filers

Company Tier BTC mined L0 Direct NET/BTC L1 Cash operating/BTC Realized price Note
TeraWulf (WULF) 1 186 $52,634 $77,976 $71,204 E scope (electricity only, grossed for DR); small volume; DER D&A incl. accelerated; mining marginal next to HPC leasing
IREN (IREN) 1 402 $44,776 $78,686 $69,652 E+S* scope; BTC revenue share falling fast (49% Q2 → 12% Q3 2026) as AI Cloud scales and mining is decommissioned; allocated overhead likely overstated; REV D&A HIGH uncertainty; filing rounded to $1m from Q1 FY27; sub-threshold from Q3 2026
Core Scientific (CORZ) 1 174 $72,310 $80,675 $70,477 E+S scope; self-mining minority and winding down (fleet held for sale); SEG D&A (mostly infrastructure once miners stop depreciating); small volume
Cipher Digital (ex-Cipher Mining) (CIFR) 1 297 $34,973 $135,614 $70,199 E+S scope; two segments from Q3 2026 (rev share 100% → 78%); HPC-construction interest allocated by revenue share → L2 not comparable; segment D&A from Q3 2026; operational KPIs only from the 8-K investor deck
American Bitcoin (ABTC) 2 891 $42,114 $44,779 $71,105 100% hosted at Hut 8 under related-party MCSA/MMSA (fixed fee + variable pass-through). Cost base embeds host margin.
Bit Digital (BTBT) 2 28.4 $51,901 $102,873 $71,197 Hosted miners, winding down; immaterial volume; shown for completeness.
Keel Infrastructure (ex-Bitfarms) (KEEL) 3 259 n/a n/a $73,031 Consolidated cost of revenues covers mining + power plants + electrical services; mining-only cost not disclosed.
Hut 8 (HUT) 3 891 n/a n/a $71,107 Consolidates ABTC, so the 891 BTC mined in the quarter are the same coins as ABTC's (not additive; bitcoin held differs by entity — see the NAV tables); 'Compute' cost of revenue mixes ASIC Compute, Traditional Cloud and AI Cloud — ASIC piece not disclosed.
Cango (CANG) 2 656 $73,313 $83,112 $72,298 PENDING — Q3 2026 report not filed at the data cut; figures are Q2 2026, carried forward until the filing; Fleet hosted at third-party sites under all-in hosting fees (electricity embedded); 6-K/20-F filer; mining-segment energy & hosting cost = company-reported average cash cost per BTC × BTC (cross-checked to the 20-F 'energy and hosting costs' line).
BitFuFu (FUFU) 3 192 n/a n/a $72,917 PENDING — Q3 2026 report not filed at the data cut; figures are Q2 2026, carried forward until the filing; Cloud-mining platform with self-mining on owned + leased hashrate; 6-K/20-F filer; cost of revenues is disclosed by counterparty (Bitmain / third parties / D&A), not by stream — self-mining direct cost not separable.
CleanSpark (CLSK) 1 n/a n/a n/a n/a PENDING — Q3 2026 not yet filed at the data cut; Q2 2026 carried forward on the charts and in the tables (marked Q2 2026) until the filing; no new estimate

Trailing four quarters (Q4 2025 – Q3 2026), production-weighted

Company Tier BTC mined 4Q Energy/BTC L0 Direct NET/BTC L1 Cash operating/BTC L3 Full/BTC Realized price Cash op. margin
ABTC 2 3,423 n/a $40,276 $46,942 $79,103 $79,115 +41%
BTDR 1 10,255 $41,443 $46,426 $57,042 $100,328 $77,552 +26%
IREN 1 4,438 $28,109 $31,327 $61,127 $128,173 $84,106 +27%
HIVE 1 3,834 $49,244 $54,896 $63,919 $117,389 $79,159 +19%
RIOT 1 6,021 $49,110 $48,081 $69,109 $115,191 $78,618 +12%
MARA 1 8,767 $41,510 $67,181 $88,514 $182,111 $79,276 -12%
CIFR 1 1,686 n/a $35,466 $94,040 $279,080 $83,176 -13%
WULF 1 795 $74,092 $43,274 $127,288 $314,886 $82,024 -55%
CANG (carried, Q3 2025 – Q2 2026) 2 5,571 n/a $80,290 $84,983 $110,487 $96,768 +12%
CLSK (carried, Q3 2025 – Q2 2026) 1 7,491 $48,008 $48,064 $64,832 $119,485 $90,675 +29%

CLSK and CANG are carried forward at their latest published four-quarter window (Q3 2025 – Q2 2026) until their next filings. Omitted where any of the four quarters is not computable: CORZ, BTBT. Tier 3 companies have no stack.

Energy layer by quarter ($/BTC)

Company Q3 2026 Q2 2026 Q1 2026 Q4 2025 Q3 2025 TTM
RIOT $45,723 $46,313 $49,095 $56,667 $58,585 $49,110
MARA $39,674 $38,690 $40,047 $48,611 $39,235 $41,510
CLSK n/a (Q2 2026 carried) $44,432 $45,486 $52,579 $49,584 $48,008
HIVE $42,617 $45,717 $51,712 $58,824 $52,646 $49,244
IREN $34,826 $22,978 $21,134 $35,406 $37,189 $28,109
CORZ $60,247 $59,339 $69,216 $66,720 $66,295 $64,887
WULF $69,839 $60,045 $83,393 $80,744 $64,183 $74,092
BTDR $36,083 $36,377 $49,090 $52,660 $50,225 $41,443
BTBT $39,648 $35,625 $45,940 n/a n/a n/a

Liquidity at 30 Sep 2026 (from the same filings)

Company Balance sheet Cash $m BTC held Debt principal $m Net debt (debt − cash − BTC@spot) $m Quarters of L1 covered by cash
RIOT 30 Sep 2026 669 2,418 675 -160 7.1x
CLSK (carried, 30 Jun 2026) 30 Jun 2026 203 13,924 1,812 659 1.7x
CANG (carried, 30 Jun 2026) 30 Jun 2026 10 1,056 49 -33 0.2x
FUFU (carried, 30 Jun 2026) 30 Jun 2026 22 1,617 99 -33 n/a
MARA 30 Sep 2026 947 34,012 3,047 -221 5.1x
HIVE 30 Sep 2026 139 269 275 118 2.3x
IREN 30 Sep 2026 3,522 0 10,041 6,519 111.3x
CIFR 30 Sep 2026 656 310 6,016 5,339 16.3x
CORZ 30 Sep 2026 804 32 4,385 3,579 57.3x
WULF 30 Sep 2026 1,602 18 5,725 4,122 110.5x
BTDR 30 Sep 2026 164 47 1,948 1,782 0.9x
ABTC 30 Sep 2026 7 8,427 0 -583 0.2x
BTBT 30 Sep 2026 143 4 566 422 49.1x
KEEL 30 Sep 2026 816 0 1,050 234 n/a
HUT 30 Sep 2026 157 16,787 7,726 6,424 n/a

BTC is valued at $68,249.27 (BTC-USD daily close 2026-11-13, Yahoo research feed; the same price and date as the Capacity base daily roll, capacity_daily.json, as_of 2026-11-13) in every row, so net debt is one market date across the table, while cash, debt and BTC held are those of each company's own balance sheet date shown in the second column (30 Sep 2026, or 30 Jun 2026 where the quarter is carried forward). Rows carried forward were first published at the 15 Oct 2026 BTC price ($82,308.83); on 19 Nov 2026 they were recomputed at the common price (CleanSpark 463 → 659, Cango −48 → −33, BitFuFu −57 → −33, $m), and they are replaced when the issuer files. Net debt counts all bitcoin held at spot, including bitcoin that is pledged or lent: pledged and lent bitcoin are not yet shown separately. 'Quarters covered' = unrestricted cash ÷ (Q3 L1 × Q3 BTC): it measures cash against the mining operating layer only, not against capital expenditure, debt service or data-center cash flows, so a high multiple (IREN, WULF, CORZ) means that mining L1 is small against cash and is not a company runway; it is a yardstick, not a forecast. Debt = principal of instruments outstanding at the balance-sheet date; post-quarter issues and repayments are not included here.

How the numbers are built

  1. Sources. SEC EDGAR only: XBRL instance facts (including segment dimensions) from 10-Q/10-K, primary-document text for MD&A KPIs, 6-K releases for foreign private issuers (BTDR, CANG, FUFU). No analyst data; no external price in the cost layers.
  2. L0-E energy / BTC — electricity component of BTC-mining cost of revenue (gross of credits) ÷ BTC mined (owned-site BTC where the energy figure covers owned sites only, e.g. MARA).
  3. L0 direct cost / BTC — segment cost of revenue excluding D&A as booked, gross of curtailment / demand-response / power-sale credits, which are shown separately; NET = gross − credits. Scope codes record what each company's line contains; no cross-company harmonization by estimate.
  4. L1 cash operating cost / BTC (headline) — L0 NET + cash SG&A run-rate (reported SG&A − SBC booked in SG&A − other disclosed non-cash items − disclosed non-recurring cash items) allocated by BTC revenue share. The band shows the same metric at 0 % and 100 % allocation; the cost-share key is in the workbook.
  5. L2 adds P&L interest expense (accrual) by revenue share; L3 adds D&A attributable to mining (segment / miner-class D&A where disclosed; derived from the company's own cost-to-mine incl. vs ex-D&A; otherwise revenue share of consolidated D&A — flagged). A run-rate L3 removes disclosed accelerated depreciation.

Terminology. "Realized price" in the tables is revenue recognized in the period from bitcoin mining ÷ BTC mined in that period (accounting revenue per coin; it is not a market price on one date and not a sale price). L1 is a normalized operating-expense measure per BTC, not a cash-flow figure: it takes booked cost of revenues and SG&A and removes the non-cash and non-recurring items listed above. L2 includes interest accrued in the income statement, not interest paid. 6. Materiality and timing. Headline set = Tier 1 owner-operators with ≥ 500 BTC mined in the quarter. Hosted miners (ABTC at Hut 8 under a related-party fee; CANG under third-party all-in hosting; BTBT) are Tier 2; KEEL, HUT and FUFU (mining cost not separable in the filings) are Tier 3 and carry no stack. A company whose quarter is not filed at the data cut is PENDING — nothing new is estimated; its latest published quarter is carried forward on the charts and in the tables, labelled with that quarter and kept outside the cohort statistics, until the filing is added within one business day (interim update; carry-forward rule, owner decision 17 Nov 2026). The quarterly re-base follows the approved calendar. 7. Verification. LibreOffice recalculation (zero formula errors) → independent Python engine recomputes every derived cell (no Excel formulas executed) → blind second-pass re-extraction of text-sourced Q3 2026 inputs (values hidden from the verifier; confidence flags XBRL / TEXT-2x / TEXT-1x / MISMATCH) → reconciliation with company-reported cost-to-mine and price metrics → arithmetic integrity checks (component sums, segment sums, YTD − prior YTD). Prior quarters keep the values and confidence flags of the previous release (its inputs file is the base of this one).

Reconciliation with issuers' own metrics

Company Issuer metric (Q3 2026) Issuer value Standard value Δ Why
RIOT 30 Sep 2026 Cost to mine ex-depreciation (net of curtailment) $39,265 $39,265 -0
RIOT 30 Sep 2026 Cost to mine incl. miner depreciation $78,805 $78,805 +0
WULF 30 Sep 2026 Cost to mine (net of demand response) $52,774 $52,634 -140
MARA 30 Sep 2026 Purchased energy cost per BTC (owned sites) $39,674 $39,674 -0

Data-quality notes (release note)

  • WARN — Realized price (rev ÷ BTC) vs reported avg price · MARA Holdings, Inc. Q1_2026: derived 78,255 vs reported 76288. Recognition-price vs revenue/BTC; gross vs net BTC counts; denominator adjustments (MARA ex-ADGM).
  • WARN — L0 Direct NET/BTC vs reported cost-to-mine ex-D&A · Core Scientific, Inc. Q3_2025: derived 87,578 vs reported 79002. Scope differences (CLSK energy+utilities on gross BTC; WULF net of DR) explain residuals.
  • Headline set changed with the data cut, not with the method. Q3 2026 has four headline owner-operators (BTDR, HIVE, RIOT, MARA) against six in Q2 2026: CleanSpark's fiscal Q4 (10-K FY2026) was not filed at the cut and IREN mined 402 BTC (threshold 500) as its fleet is decommissioned for AI Cloud. Cohort statistics are therefore not comparable release to release — use the like-for-like line in the Headline block or the trailing-four-quarter table.
  • Pending filers (latest published quarter carried forward, owner decision 17 Nov 2026): CLSK (10-K FY2026, expected ≈ 24 Nov 2026), CANG and FUFU (Q3 results 6-K not yet furnished). Their rows are marked PENDING; the previous release (2026Q2) supplies their last published figures, which are shown labelled and outside the cohort statistics (CLSK shown; CANG and FUFU are carried in the appendix, TTM and liquidity tables). They are added within one business day of the filing (interim-update rule, owner decision 15 Nov 2026).
  • Presentation changes picked up in Q3 2026 filings: CIFR now reports two segments (Bitcoin Mining / HPC Leasing) with a first segment D&A split (used as SEG) and ~$0.9m of 1H cost of revenue recast into the HPC line (prior quarters not restated here); IREN switched its statements to $ millions (inputs carry ±$0.5m rounding — material for a 402-BTC quarter) and dropped the net-electricity / demand-response table; CORZ moved advisor fees out of SG&A into a separate line and its mining fleet is held for sale (segment depreciation is mostly infrastructure); BTDR changed its hashrate presentation ('Total Proprietary Hash Rate' excludes co-mining; self-mining 82.3 EH/s kept for continuity) and its segment electricity lines no longer reconcile to MWh × $/kWh (151.1m vs 145.6m); RIOT relabelled 'Ground and facility rent, water, and property tax' and its segment cost lines now carry $0.7m of 'other segment items' (consolidated MD&A components used); HIVE booked its first mining-fleet impairment ($31.2m, excluded from every layer); ABTC began selling BTC to fund operations and its G&A fell to $2.8m (9M reconciles); KEEL sold its entire BTC treasury and 26% of its revenue is now energy sales; HUT's consolidated BTC now equals ABTC's.
  • Derivations worth knowing (all cited in the Data sheet): CIFR Q3 BTC mined = 9M 1,095 − 6M 798 = 297 (holdings roll-forward 646 + 297 − 633 = 310 matches the balance sheet exactly); CORZ Q3 BTC mined = 9M ≈869 − 6M ≈695 = 174 (both 'approximately'); MARA denominator 2,247 − 30 ADGM equity-method BTC = 2,217, energy layer on 1,213 owned-site BTC; BTDR direct cost = self-mining 121.0m + co-mining 38.3m against 3,855 BTC incl. co-mining; WULF energy grossed up for $3.2m demand-response proceeds (MD&A 'gross power costs $13.0m' reconciles); WULF D&A attributable from the MD&A miner-fleet footnote ($50,790 × 186), accelerated depreciation $7.7m (miner building, related miners and electrical equipment — split not disclosed, treated as inside); cash interest 3M = 9M − 6M with the 6M taken from the previous release's inputs.
  • Liquidity layer now comes from the same Q3 filings (balance sheet, debt and crypto-asset notes), not from the NAV data set; BTDR's 6-K gives carrying amounts only (principal not disclosed — carrying used, flagged); BTC valued at the 13 Nov 2026 close used by the site's daily value-per-MW roll, so the two mining bases share one spot.
  • Prior quarters are unchanged: the 2026Q2 inputs file (SHA-256 7922aeb6…) is the base of this release; its values and blind-verification flags are carried over untouched and only Q3 2026 inputs were extracted and verified anew.

Filings used

Company Q3 2026 Q2 2026 Q1 2026 Q4 2025 Q3 2025
Riot Platforms (RIOT) 10-Q 10-Q 10-Q 10-K · derived 12M−9M 10-Q
MARA Holdings (MARA) 10-Q 10-Q 10-Q 10-K · derived 12M−9M 10-Q
CleanSpark (CLSK) — (pending) 10-Q Q3 FY2026 10-Q Q2 FY2026 10-Q Q1 FY2026 10-K Q4 FY2025 · derived 12M−9M
HIVE Digital (HIVE) 10-Q Q2 FY2027 10-Q Q1 FY2027 10-K Q4 FY2026 6-K Q3 FY2026 6-K Q2 FY2026
IREN (IREN) 10-Q Q1 FY2027 10-K Q4 FY2026 · derived 12M−9M 10-Q Q3 FY2026 10-Q Q2 FY2026 10-Q Q1 FY2026
Cipher Digital (ex-Cipher Mining) (CIFR) 10-Q 10-Q 10-Q 10-K · derived 12M−9M 10-Q
Core Scientific (CORZ) 10-Q 10-Q 10-Q 10-K · derived 12M−9M 10-Q/A
TeraWulf (WULF) 10-Q 10-Q 10-Q 10-K · derived 12M−9M 10-Q
Bitdeer (BTDR) 6-K 6-K 6-K 6-K 6-K
Cango (CANG) — (pending) 6-K 6-K 6-K 6-K
BitFuFu (FUFU) — (pending) 6-K 6-K 20-F · derived 12M−9M 6-K
American Bitcoin (ABTC) 10-Q 10-Q 10-Q 10-K · derived 12M−9M 10-Q
Bit Digital (BTBT) 10-Q 10-Q 10-Q — —
Keel Infrastructure (ex-Bitfarms) (KEEL) 10-Q 10-Q 10-Q — —
Hut 8 (HUT) 10-Q 10-Q 10-Q 10-K · derived 12M−9M 10-Q

Accession numbers, filing dates and the XBRL concept / verbatim quote behind every input are in the workbook (Data and Sources sheets).

Model integrity

  • Standard version: 1.0
  • Data as of (latest quarter): 2026Q3 — filings through 2026-11-12 (BTBT)
  • Periods: Q3_2026, Q2_2026, Q1_2026, Q4_2025, Q3_2025 (TTM = Q3_2026, Q2_2026, Q1_2026, Q4_2025)
  • Companies: RIOT, MARA, CLSK, HIVE, IREN, CIFR, CORZ, WULF, BTDR, CANG, FUFU, ABTC, BTBT, KEEL, HUT; PENDING at cut: CANG, CLSK, FUFU
  • LibreOffice recalc: success — 5378 formulas, 0 errors
  • Engine compare: 1932 derived values, 1932 match, 0 mismatch — OK
  • Checks: 139 PASS / 2 WARN / 0 ERROR
  • Blind verification: TEXT-1x: 370, TEXT-2x: 327, XBRL: 415
  • Verdict: READY
  • Validated at (UTC): 2026-11-15 13:10 UTC
  • Inputs fingerprint (SHA-256 normalized.json): 1fcfd65b9fa8847040848b09f5d638765993aec1544be967305ee6d043098c6b

Disclaimer

  1. Informational research; not investment advice, not an offer or solicitation; no recommendations, target prices or signals are made or implied.
  2. Results are model outputs derived from the issuers' public filings and the stated assumptions under the published Standard; definitions may differ from issuers' own metrics and from other providers. Past data and hypothetical figures do not predict future results.
  3. Sources are cited per input; figures may be revised when issuers restate or when errors are found. Errata are published above the page and prior versions are retained with their fingerprints.
  4. Conflict of interest: the author may hold positions in the companies covered; the existence of a position is disclosed on the publication page, its size is not; no trading in the covered securities ±2 trading days around publication.
  5. Readers are encouraged to reproduce the results from the files listed on this page. See also the general disclaimer.