DIGITAL INFRASTRUCTURE / INVESTMENT INTELLIGENCERESEARCH PLATFORM · DATA CENTER FULL CYCLE INDEX · DATA AS OF 23 NOV 2026 · PUBLICATION LOG
MINING · VALUATION · EDITION 0.9.6 · COMPANY REPORT

Riot Platforms, Inc. (RIOT): what a share is worth

How the value per share of Riot Platforms, Inc. is built in three scenarios: every signed lease with its source, every megawatt the company reports, the chance of new leases, its mining sites and its balance sheet. Data as of 18 Nov 2026.

Edition 0.9.6 · published 21 Nov 2026Data as of 18 Nov 2026Checks passed: 0 errorsInput fingerprint b40059cbfd59…

Edition 0.9.6. Values are model results from company filings, company statements and dated market data, before tax (exception VX-2026-02 to the equity valuation standard), not price targets; nothing here is investment advice.

$32.05value per share, central scenario
$19.66 – $46.65cautious to optimistic; weighted average $32.49, +78% against the share price
$18.24share price on 18 Nov 2026 (data cut), below the range. Latest close $17.15 on 23 Nov 2026 (−6.0%): weighted average +89% against it
11.6%cap rate on the signed leases that matches the share price
Checked. Calculated three ways — engine, spreadsheet of formulas and a separate script from the text of the standard — with no difference larger than 0e+00 dollars a share. Compared with 2 other pages of the site that show RIOT: 12 figures agree, 1 differ for a stated reason. See the list →

Summary

In the central scenario the model values Riot Platforms, Inc. at $32.05 a share; the share price was $18.24 on 18 November 2026. Per share the value adds up as follows: signed leases $30.57, the chance of new leases on capacity that has none yet $0.37, mining sites at the cost to rebuild them $0.70, mining machines $0.61; less company overhead $0.80; plus cash and bitcoin net of debt $0.60.

Across the three scenarios the value runs from $19.66 (cautious) to $46.65 (optimistic). Weighting them 20%, 60% and 20% gives $32.49, 78% above the share price; the price is below the range. The central scenario supplies 59% of the weighted average.

The share price is consistent with valuing the signed leases at an 11.6% cap rate (a year's operating income divided by the property value), against 6.5% for investment-grade tenants and 8.5% for other tenants in the central scenario. A higher cap rate means a lower value.

The share price is below the value of the signed leases and the mining sites as they are, so it includes nothing for new leases on the capacity that has none yet.

Leasing all convertible capacity would need about $5.46bn of building work, 0.8 times the company's stock-market value, and would give $33.06 a share in the central scenario. In the cautious scenario new building does not pay for itself, so the value with all capacity leased is $19.66.

587 MW of mining sites are counted at $0.45m per MW, the cost to rebuild them without the machines: $264m in total. At $0.5m per MW, the level at which operating sites sold in 2026, the central value would be $32.10 a share.

How the value adds up

Central scenario, US dollars per share

Green adds, orange subtracts; the blue bar is the value per share before the floor at zero; the dashed line is the share price on 18 Nov 2026.

Riot Platforms, Inc.: how the central value per share adds upBars in US dollars per share for the central scenario: each part adds or subtracts, the last bar is the value per share; the dashed line is the share price.$0$10$20$30Signed leases: $30.57 per share ($11.47bn)$30.57LeasesChance of new leases on capacity without a lease: $0.37 per share ($137m)$0.37NewleasesMining sites at the cost to rebuild them: $0.70 per share ($264m)$0.70MiningsitesMining machines at market value: $0.61 per share ($228m)$0.61MachinesCompany overhead: −$0.80 per share (−$300m)−$0.80OverheadCash and bitcoin, less debt and other claims: $0.60 per share ($226m)$0.60Cash lessdebtValue per share before the floor at zero: $32.05$32.05Valueshare price$18.24
Part of the valueCautious, totalCentral, totalOptimistic, totalCautious, $ a shareCentral, $ a shareOptimistic, $ a share
Signed leases$7.25bn$11.47bn$15.74bn$19.33$30.57$41.94
GPU cloud contracts$0m$0m$0m$0.00$0.00$0.00
Chance of new leases on capacity without a lease$0m$137m$864m$0.00$0.37$2.30
Mining sites at the cost to rebuild them$176m$264m$528m$0.47$0.70$1.41
Mining machines at market value$171m$228m$398m$0.46$0.61$1.06
Company overhead−$450m−$300m−$250m−$1.20−$0.80−$0.67
Construction money already raised and set aside$0m$0m$0m$0.00$0.00$0.00
Money owed by related parties$0m$0m$0m$0.00$0.00$0.00
Cash and bitcoin, less debt and other claims$226m$226m$226m$0.60$0.60$0.60
Value of the shares$7.38bn$12.02bn$17.50bn$19.66$32.05$46.65

375.2 million shares, including warrants that cost almost nothing to exercise. Value per share never goes below zero; the chart shows the value before that floor. Stock-market value of the company: $6.84bn.

How each block is valued for RIOT

The ten blocks of the standard, in order, with what is counted for Riot Platforms, Inc., its central value per share and the findings of this edition's review. OK rules met with company documents · Limit a known limit of the method · Open a document, figure or decision is needed · Fix a rule is broken.

Block and ruleWhat is countedCentral, $ a shareStatusFindings
Signed leasesA year of operating income ÷ cap rate by tenant credit, discounted to the year the lease is fully running, less construction still to pay.4 leases, 1,151 MW of server load$30.57Open
  • Rockdale, Texas — AMD, 25 MW, 10 years: a 10-year lease at the investment-grade cap rate; the cap rate does not see the end of the term (a cash-flow test over the term comes with version 1.0).
  • Rockdale, Texas — AMD expansion, 25 MW: terms rest on our own estimate; a company filing or release is needed.
  • Rockdale, Texas — AMD expansion, 25 MW: a 10-year lease at the investment-grade cap rate; the cap rate does not see the end of the term (a cash-flow test over the term comes with version 1.0).
  • Rockdale, Texas — AI lab (name not disclosed), 191 MW, 20 years: construction cost not disclosed; the standard $11.9m per megawatt of server load is used.
GPU cloud contractsCash margin over the contract, plus what the GPUs are worth at the end, less the GPUs not yet delivered.none$0.00OK—
Capacity breakdownEvery megawatt the company reports in one status; the statuses add up to the company's total within 0.5%.2,000 MW of grid power in 7 statuses—Open
  • Rockdale, Texas — capacity not under lease: 355.0 MW is our estimate (company total less the sites it lists).
Capacity without a leaseChance of a lease × (data-centre value after its full build cost − the mining site it replaces), never below zero.655 MW that could be leased$0.37Limit
  • Chances of a lease for powered sites (30% central, calibrated on observed leasing, rule B4.5) and the pipeline (5% central, our assumption) are one chance per status, reviewed for version 1.0.
Mining sitesOperating mining megawatts × the cost to rebuild one megawatt, without machines; leased megawatts carry no mining value.587 MW$0.70Limit
  • 587 MW at $0.45m per MW, the cost to rebuild from filed build costs (rule B5.4); operating sites sold for about $0.4–0.7m per MW including machines in 2026.
Mining machinesFleet value from the site's miner net asset value standard, or installed hashrate × $7.05 per terahash per second.$228m$0.61OK—
Company overheadA landlord's yearly overhead × 10, the same for every company.$300m−$0.80Limit
  • $30m a year × 10 in the central scenario for every company; the company's own overhead and share-based pay are used from version 1.0.
Construction money and other assetsConstruction money already raised and set aside is deducted; money owed by related parties counts only in the optimistic scenario.—$0.00OK
  • Nothing to count.
Debt, cash and bitcoinDebt at face value, outside shareholders and customer prepayments are subtracted; cash and bitcoin at market are added.balance sheet of 30 September 2026$0.60Limit
  • 4 figures updated after the balance sheet from filed documents (the site's interim inputs).
  • Values are before tax, as for a real-estate investment trust; a tax deduction comes with version 1.0.
SharesShares outstanding plus warrants that cost almost nothing to exercise.375.2 million—OK
  • 375.2 million shares.

The values add up to the central value per share before the floor at zero ($32.05). Findings marked «Open» are also listed under Open points when they concern a figure of this report.

Signed leases and GPU cloud contracts

LeaseMW of server loadContract valueTermOperating income, year 1 (central)Tenant creditCap rate (central)Fully running fromConstruction still to pay (central)Value, cautiousValue, centralValue, optimisticSource of the terms
Rockdale, Texas — AMD, 25 MW, 10 yearsOperating income of about $25m a year, as disclosed. Already delivered.25$311m10 years, rent +3% a year$25minvestment grade6.5%1 Jun 2026 (delivered)$0m$333m$385m$417mCompany filing
Rockdale, Texas — AMD expansion, 25 MWOur estimate: the contract value is not disclosed, so the terms of the first AMD lease are used; 10 MW from November 2026 and 15 MW from May 2027, as filed; conversion cost $3.6m per MW, as disclosed for the first phase.25$311m10 years, rent +3% a year$25minvestment grade6.5%1 May 2027$90m$205m$283m$316mOur estimate
Rockdale, Texas — AI lab (name not disclosed), 191 MW, 20 years$9.1bn contract running to June 2048; operating margin of 80–90% disclosed (85% used). The tenant has no disclosed credit rating.191$9.10bn20 years, rent +3% a year$288mnot investment grade8.5%1 Jul 2028$2.27bn$140m$855m$1.64bnCompany filing
Corsicana, Texas — AI lab (name not disclosed), 910 MW, 15 yearsStarting rent of $130 per kilowatt per month with 3% yearly increases and about 99% operating margin (a triple-net lease of land and power): $1.41bn of operating income in the first year. Handover in three phases: 400 MW in September 2027, 200 MW in January 2028, 310 MW in July 2028. Build cost $6m per MW — $2m of Riot's own works plus up to $4m reimbursed to the tenant — $5.5bn in total, 10% more in the cautious case. Binding since 4 November 2026; the tenant has no disclosed credit rating.910$28.00bn15 years, rent +3% a year$1.41bnnot investment grade8.5%1 Jan 2028$5.46bn$6.57bn$9.94bn$13.36bnCompany filing

Operating income, year 1: the figure the company discloses, or the first-year rent times the operating margin; where only the total contract value is known, the first-year rent is worked back from it with the yearly rent increase. Cap rate: a year's operating income divided by the property value; it is lower for tenants with an investment-grade credit rating. Source of the terms: a company filing or statement confirms a lease; terms from a secondary source or our own estimate are marked and listed as open points until a filing confirms them. The documents behind each lease are listed under Sources.

Capacity breakdown

Total: 2,000 MW of grid power. Texas 1,700 MW (Rockdale 700, Corsicana 1,000) and Kentucky 300 MW (presentation for the third quarter of 2026). The statuses below add up to 2,000.0 MW (difference +0.0).

StatusMWof which mining sitesMining sites (central)Value with the chance of a lease (central)Value if all leased (central)Build cost if all leased (central)
Signed leaseA signed lease or colocation contract for an AI or high-performance computing data centre.1,345.0——$11.47bn$11.47bn—
Powered, no tenantPower is connected or contracted, but there is no tenant.587.0587.0$264m$397m$709m$4.89bn
PipelineGrid queue, development, due diligence or a purchase not yet closed: no power under the company's control and no tenant yet.68.0——$4m$73m$566m

For signed leases and GPU cloud contracts the value columns show the contracts themselves. For the other statuses they show the mining sites plus what a new lease would add over them.

Capacity without a lease

Site or groupStatusMWCompany's shareMining sites, MWChance of a lease: cautious / central / optimisticData-centre value (central)Mining sites (central)Added value with the chance (central)Added value if leased (central)Build cost if leased (central)
Rockdale, Texas — capacity not under lease our estimateOur estimate: 700 MW developed less 345 MW under lease. Developed and mining today.Powered, no tenant355.0100%355.010% / 30% / 50%$429m$160m$81m$269m$2.96bn
Kentucky — mining sites in operationDeveloped and mining today.Powered, no tenant232.0100%232.010% / 30% / 50%$280m$104m$53m$176m$1.93bn
Kentucky — further capacity without a datePipeline68.0100%—0% / 5% / 15%$73m—$4m$73m$566m

Data-centre value: the company's share × megawatts of server load × what one megawatt of AI data centre is worth after paying its full build cost. In the central scenario that is $1.72m per megawatt of server load for powered sites and sites with a letter of intent, and $1.54m for the pipeline; in the cautious scenario it is zero, because new building does not earn its cost. Server load is taken as 70% of grid power in the central scenario. Added value = chance of a lease × (data-centre value − mining sites it replaces), and never below zero.

If all capacity were leased

MeasureCautiousCentralOptimistic
Added value with the chance of a lease, $ a share$0.00$0.37$2.30
Added value if all capacity were leased, $ a share$0.00$1.38$5.04
Value per share with the chance of a lease$19.66$32.05$46.65
Value per share if all capacity were leased$19.66$33.06$49.38

Weighted average if all capacity were leased: $33.64. Building it would cost $5.46bn in the central scenario, 0.8 times the company's stock-market value. Share of the unleased capacity that the share price treats as leased: none — the price is below the value of what is signed and the mining sites as they are.

Central value per share against the share of unleased capacity that gets leased

The same chance applied to every site without a lease (letters of intent, powered sites without a tenant, pipeline); the dashed line is the share price.

Riot Platforms, Inc.: central value per share against the share of unleased capacity that gets leasedCentral value per share if the same chance, from 0% to 100%, applied to all capacity without a lease (letters of intent, powered sites without a tenant, pipeline); the dashed line is the share price.$0$7$15$22$29$360%20%40%60%80%100%0% of the capacity without a lease leased: $31.68 a share10% of the capacity without a lease leased: $31.82 a share20% of the capacity without a lease leased: $31.96 a share30% of the capacity without a lease leased: $32.09 a share40% of the capacity without a lease leased: $32.23 a share50% of the capacity without a lease leased: $32.37 a share60% of the capacity without a lease leased: $32.51 a share70% of the capacity without a lease leased: $32.65 a share80% of the capacity without a lease leased: $32.78 a share90% of the capacity without a lease leased: $32.92 a share100% of the capacity without a lease leased: $33.06 a shareshare price $18.24all leased: $33.06

Mining

ItemCautiousCentralOptimistic
Operating mining sites, 587.0 MW, at the cost to rebuild them$176m at $0.30m per MW$264m at $0.45m per MW$528m at $0.90m per MW
Mining machines at market value$171m$228m$398m

Fleet value from the site's miner net asset value standard (version 1.2). The cost to rebuild a site excludes the machines. Operating sites sold in 2026 for about $0.4–0.7m per megawatt including the machines; the central value with sites at $0.5m per megawatt is under What moves the result.

Balance sheet and market data

Share price (18 Nov 2026)$18.24Balance sheet date30 Sep 2026
Debt at face value$675mCash, including cash set aside$748m
Outside shareholders in subsidiaries$0mBitcoin held2,418 BTC = $152m
Customer prepayments, counted as debt$0mConstruction money already raised (central)$0m
Shares, million375.2MW on the site's capacity pages: energised / committed / pipeline1,332 / 1,932 / 2,000

A $573m interim credit facility is left out of debt because the amount drawn is not disclosed.

What moves the result

Change, central scenarioValue per shareDifference
Central scenario as it is$32.05
No new leases on capacity without a lease$31.68−$0.37
Cap rates 0.5 percentage points lower$35.53$3.48
Cap rates 0.5 percentage points higher$28.96−$3.08
Chances of new leases doubled$32.40$0.36
Build cost 10% higher$31.16−$0.88
Mining sites at $0.5m per MW (level of 2026 site sales)$32.10$0.05
Mining sites not counted$31.55−$0.49

Updates

Data cut of this edition18 Nov 2026 (balance sheet of 30 Sep 2026; 10-Q, 10-K, 8-K)
Latest close and market value$17.15 on 23 Nov 2026; market value $6.43bn (at the data cut $18.24 and $6.84bn) — loaded every US trading day at 04:00 Moscow time
Next report expected22 Feb 2027 — Earnings release (estimated from the same report a year earlier)
Next edition due30 Nov 2026 — quarterly re-cut
Since the data cutbitcoin −2.8%; share count −0.0% (new edition when bitcoin moves more than 20% or the share count more than 5%)

SEC filings since the data cut

No filing since 18 Nov 2026 (EDGAR checked 24 Nov 2026).

Each new filing is assessed automatically for this valuation: a quarterly or annual report means a new edition within 10 business days; a new lease, letter of intent, GPU contract, financing or closed purchase within 5. All filings of RIOT are in the SEC filings feed; the order of updates is section 9 of the standard.

Does this report agree with the rest of the site?

Every figure that another page of the site also shows for RIOT, side by side. Same: equal within rounding. Explained: different by rule — a later share price on a daily page, face value of debt here against carrying value on the company card, issues or repayments after the balance sheet, another source for the share count. To check: a difference without a stated reason.

PageWhat is comparedThis reportOther pageResult
Valuation summary tableValues per share in the table of all companies$32.05 central$32.05 centralSame
This reportParts of the value add up to the value of the sharesthree scenariossum of the partsSame
Formula workbookSame numbers in the spreadsheet of formulas840 values, all companies0 differencesSame
Independent recomputationSame numbers from a separate script written from the standard4 valueslargest difference 0e+00Same
Value per MWBalance-sheet date2026-09-302026-09-30Same
Value per MWDebt, $m674.5674.5Same
Value per MWCash incl. restricted, $m748.2748.2Same
Value per MWBitcoin held2,4182,418Same
Value per MWMW operating (D1)1,332.01,332.0Same
Value per MWMW of grid power (D3)2,0002,000Same
Value per MWShares, million375.2375.2Same
Value per MWShare price$18.24 on 2026-11-18$17.15 on 2026-11-23Explained the daily page shows the latest close; this edition uses the close of its data cut (shown as Latest close on this page)
Miner NAVMining machines at market value, $m228.4228.4 (NAV v1.2, 2026-11-16)Same

Open points

  • Rockdale, Texas — AMD expansion, 25 MW: the lease terms rest on our own estimate; a company filing is needed to confirm them.
  • Rockdale, Texas — capacity not under lease: 355.0 MW is our estimate (the company's total less the sites it lists), not a figure the company gives.

Sources

  1. Current report on form 8-K of 16 January 2026, exhibit 99.1 — sec.gov
  2. Quarterly report on form quarterly report (form 10-Q) for the second quarter of 2026 (April 2026 amendment; value not disclosed) — sec.gov
  3. Current report on form 8-K of 10 August 2026, exhibit 99.1 — sec.gov
  4. Current report on form 8-K of 4 November 2026, exhibit 99.1 — sec.gov
  5. Our estimate
  6. Quarterly report for Q3 2026 (form 10-Q), as recorded in the site's capacity data
  7. Presentation for Q3 2026, as recorded in the site's capacity data
  8. Share price, balance sheet and capacity: the site's market data file of 18 Nov 2026 (src/data/mining/capacity_daily.json, frozen copy).
  9. Latest close: the same market data file as it rolls daily (src/data/mining/capacity_daily.json); it moves the price comparison only, not the value per share.
  10. Assumptions and their sources: assumptions of the three scenarios; rules: the standard.

Data behind this report

This report as data: riot.json · input fingerprint b40059cbfd5980d94d9590bd49d20b176a680e9f969aca8e51c409f4e8acd084 · data passport · reproduction kit.